July 8th Update

Our construction plans for this and next week cover the following staking sheets. They are highlighted in yellow below.

Red Oak – This week crews will be working in the area of sheets 57, 60, 61, 62, 63, 66 and 67. Next week the plan is to work on sheets 30, 58, 64, 68, 69, 70 and 73.

Crews will be arriving this week to start installing drops to houses. They will be working in areas that the main line construction is completed.

Clarinda – Crews will be continuing in the area of sheets 14, 18, 19, 20, 21 and 22. Their plan is to next go to sheets 10, 11, 12 and 13.

Red Oak

Clarinda

Douglas Pals
July 1st Update

Our construction plans for this and next week are the same as last week. This will be a short week for the construction crews as they return home to enjoy the holiday.

There won’t be any open holes and equipment will be moved out of the way so residents can enjoy the holiday also.

Douglas Pals
June 24th Update

Our construction plans for this and next week cover the following staking sheets. They are highlighted in yellow below.

Red Oak – Crews will be finishing main line construction in the area of sheets 13, 14, 15 and 29. Once that is done, they’ll move to sheets 57, 59, 60, 61, 62, 63, 66 and 67.

Red Oak – Crews will be arriving the week of July 8th to start installing drops to houses. They will be working in areas that the main line construction is completed.

Clarinda – Crews will be continuing in the area of sheets 9, 21 and 22. Their plan is to next go to sheets 10, 11, 13, 14, 18, 19 and 23.

Red Oak

Clarinda

Douglas Pals
June 17th Update

Our construction plans for this and next week cover the following staking sheets. They are highlighted in yellow below.

Red Oak – This week crews will be working in the area of sheets 22, 23, 25, 26, 27, 28 and 29. Once that is done, they’ll move to sheets 13, 14 and 15.

Red Oak – Crews will be arriving this week to start installing drops to houses. They will be working in areas that the main line construction is completed.

Clarinda – Crews will be in the area of sheets 2, 3, 9, 13, 14, 18, 19, 20 and 21 this week. Their plan is to next go to sheets 8, 22 and 23.

Red Oak

Clarinda

Douglas Pals
June 10th Update

Our construction plans for this and next week cover the following staking sheets. They are highlighted in yellow below.

Red Oak – This week crews will be working in the area of sheets 19, 20, 21, 55 and 59. Once that is done, they’ll move to sheets 22, 23, 27 and 30.

Clarinda – Crews will be in the area of sheets 2 and 3 this week. Their plan is to next go to sheets 6, 7 and 21.

Red Oak

Clarinda

Douglas Pals
June 3rd Update

Our construction plans for this and next week cover the following staking sheets. They are highlighted in yellow below.

Red Oak – 1A through 20, 55 & 56. They will be finishing up the Acorn Acres area and to the west. Once that is done, they’ll move east in the Irene Ct. area.

Clarinda – Crews will be starting this week. Their plan is to start around our Central Office (CO) area on the east side of the square.

Red Oak

Clarinda

Douglas Pals
May 29th Update

Our construction plans for this and next week cover the following staking sheets. They are highlighted in yellow below.

Red Oak – 1A through 19. They are currently working in the Acorn Acres area and to the west. Once that is done, they’ll move east in the Irene Ct. area. 

Clarinda – Not started yet, they are having issues with the locators for the power company and gas company (may be the same?). They only located the mains, and not the branches. They are hoping to start yet this week. Their plan is to start around the CO area.

Red Oak

Red Oak

Clarinda

Clarinda
Douglas Pals