June 17th Update

Our construction plans for this and next week cover the following staking sheets. They are highlighted in yellow below.

Red Oak – This week crews will be working in the area of sheets 22, 23, 25, 26, 27, 28 and 29. Once that is done, they’ll move to sheets 13, 14 and 15.

Red Oak – Crews will be arriving this week to start installing drops to houses. They will be working in areas that the main line construction is completed.

Clarinda – Crews will be in the area of sheets 2, 3, 9, 13, 14, 18, 19, 20 and 21 this week. Their plan is to next go to sheets 8, 22 and 23.