July 8th Update
Our construction plans for this and next week cover the following staking sheets. They are highlighted in yellow below.
Red Oak – This week crews will be working in the area of sheets 57, 60, 61, 62, 63, 66 and 67. Next week the plan is to work on sheets 30, 58, 64, 68, 69, 70 and 73.
Crews will be arriving this week to start installing drops to houses. They will be working in areas that the main line construction is completed.
Clarinda – Crews will be continuing in the area of sheets 14, 18, 19, 20, 21 and 22. Their plan is to next go to sheets 10, 11, 12 and 13.
Red Oak
Clarinda