June 10th Update

Our construction plans for this and next week cover the following staking sheets. They are highlighted in yellow below.

Red Oak – This week crews will be working in the area of sheets 19, 20, 21, 55 and 59. Once that is done, they’ll move to sheets 22, 23, 27 and 30.

Clarinda – Crews will be in the area of sheets 2 and 3 this week. Their plan is to next go to sheets 6, 7 and 21.

Red Oak

Clarinda

Douglas Pals