June 24th Update
Our construction plans for this and next week cover the following staking sheets. They are highlighted in yellow below.
Red Oak – Crews will be finishing main line construction in the area of sheets 13, 14, 15 and 29. Once that is done, they’ll move to sheets 57, 59, 60, 61, 62, 63, 66 and 67.
Red Oak – Crews will be arriving the week of July 8th to start installing drops to houses. They will be working in areas that the main line construction is completed.
Clarinda – Crews will be continuing in the area of sheets 9, 21 and 22. Their plan is to next go to sheets 10, 11, 13, 14, 18, 19 and 23.
Red Oak
Clarinda