December 2
In Both Towns - We will finish site surveys this week for all those we can contact, there are some who are not responding. Drop crews are working to complete installing fiber to residences. Fiber connections are being spliced and tested.
Red Oak – Construction will move to Ironwood and finishing boring under streets. Installations are continuing now as we get fiber splicing test results. The Bluegrass Road area is on hold as we continue to wait on the city and railroad.
Clarinda – Main construction has been completed. We are getting the central office electronics powered and connected. We should be starting installations to customers as soon as we get verified fiber test results.