November 18 Update
In Both Towns - We are working on finishing up site surveys. Drop crews continue to install fiber to residences. Fiber connections are being spliced and tested.
Red Oak – Construction will focus on finishing up various areas and will move to Ironwood. Installations are starting now as we get fiber splicing test results. The Bluegrass Road area is on hold as we continue to wait on the city and railroad.
Clarinda – Construction will continue in the north western part of our build area.