November 4 Update
In Both Towns - We are working on finishing up site surveys. Fiber connections are being spliced and tested.
Red Oak – Construction will move to Ironwood possibly later this week or next week. Installations are starting now as we get fiber splicing test results. The Bluegrass Road area is on hold as we continue to wait on the railroad.
Clarinda – Construction will continue in the western part of our build area. There is no drop crew this week.