October 28 Update

In Both Towns - We are continuing to perform site surveys, test fiber connections and install fiber drops.

Red Oak – Main construction is wrapping up along eastern Summit, drops will be next. Construction will move to Ironwood after that. The Bluegrass Road area is now on hold as we continue to wait on the railroad.

Clarinda – Construction will continue in the western part of our build area.

Becky Collins