August 12 Update
Our construction plans for this and next week cover the following staking sheets. They are highlighted in yellow below.
Red Oak – This week is a continuation of the plans from last week.
Drop lines and main fiber lines are in the process of being installed.
Clarinda – Crews will be in the area of sheet 16, completing the main enclosures (pedestals and vaults) and duct.
Next week will start the process of installing the main fiber lines.
Drop crews should start soon.
Red Oak Map
Clarinda Map