July 29th Update

Our construction plans for this and next week cover the following staking sheets. They are highlighted in yellow below.

Red Oak – Crews are continuing to work in the areas of sheets 35, 68, 69, 70, 71, 72, 73, 74, 75, 76 and 77.

Next week’s plan is to work in 32, 33, 34, 35, 40, 41, 42 and 43.

Crews will finally be installing drops to houses starting Tuesday.

Clarinda – Crews are finished with the area along Nishna St and south. They will be finishing the areas of 13, 14 and 25. The next week should be areas 15, 17 and 16, completing the main enclosures (pedestals and vaults) and duct.

Red Oak

Clarinda

Douglas Pals